crowflight minerals

Seite 39 von 76
neuester Beitrag: 21.12.10 12:18
eröffnet am: 29.01.07 21:41 von: Ohio Anzahl Beiträge: 1878
neuester Beitrag: 21.12.10 12:18 von: dear Leser gesamt: 324964
davon Heute: 56
bewertet mit 34 Sternen

Seite: Zurück 1 | ... | 36 | 37 | 38 |
| 40 | 41 | 42 | ... | 76  Weiter  

08.05.08 07:44

9555 Postings, 6503 Tage TykoSK 0,74Can$ = 0,477?

...in D noch stark über pari.

Müßten die Canadier erst mal heute nachziehen.
-----------
Gewinn ist die Summe aus positiven Investitionen abzüglich negativer Investitionen

08.05.08 09:45

247 Postings, 6818 Tage zockerAber nicht auf unser Pferdchen Mustang vergessen,

geht auch in den Galopp über!!

der Zocker  

08.05.08 11:41

247 Postings, 6818 Tage zockerEin bisschen Luftholen

muß auch die Krähe!!

Der Zocker  

08.05.08 14:47
1

1196 Postings, 7890 Tage madxfriendnews - nicht übel - es geht voran


Press Release Source: Crowflight Minerals Inc.


Crowflight Provides Bucko Lake Nickel Project Update
Thursday May 8, 7:30 am ET


TORONTO, ONTARIO--(Marketwire - May 8, 2008) - CROWFLIGHT MINERALS INC. (Crowflight, the Company) (TSX VENTURE:CML - News) today provided a project update for the Bucko Lake Nickel Project (Bucko) that is currently under development outside Wabowden, Manitoba.

Work is progressing steadily on the surface facilities at Bucko, with much of the current activity focused on the processing plant. Most of the processing plant equipment is on-site, with some electrical components due to arrive in the next two months. The jaw and cone crusher are in place with structural steel for the crushing circuit progressing. The conveyors are on-site and the conveyor sections should be installed between now and June. Installation of the fine ore bin is expected to begin shortly. Mechanical installation of the rod and ball mill is close to completion, as is the mechanical installation of the flotation circuit. The concentrate filter is in place, electrical work on the plant's interior has begun and piping is expected to start shortly.

In addition to work on the processing plant, the area for the Interim Tailings Storage Facility (ITSF) has been cleared and the geotechnical and design work is complete.

Underground Development

The new portal for the underground ramp is progressing with completion expected by the end of May.

Two diamond drills are currently underground undertaking definition and delineation drilling on the 1,000 foot level. It is expected that the geotechnical information and assay results from this drilling should assist in optimizing the geotechnical design and upgrading the mineable reserve. The development underground on the 1,000 foot level has progressed to the point that the larger mining equipment is ready to be transported underground and then assembled to finish the remaining work on that level and the ramps to other levels.

Paul Keller, Crowflight's VP of Operations and COO, said: "A tremendous amount of progress has been made at Bucko since beginning construction in November 2006. Our staff, contractors and consultants have been working tirelessly to bring Bucko into production in the third quarter of 2008 and we look forward to achieving this goal."

The operating costs, including on-site and off-site costs, are projected to be $4.32 per pound of nickel produced, using a US$:Cdn$ exchange rate of 1:1.The capital cost for the Bucko Lake Nickel Deposit development is now expected to be Cdn$86 million net of pre-production revenue, assuming a US$:Cdn$ exchange rate of 1:1. This compares to the Feasibility Study estimate of Cdn$66.0 million at an exchange rate of 0.8:1.

The cost differences are attributable to the following: Cdn$6.7 million due to capital development timing, the addition of the ITSF, the ramp portal and surface connection to the underground internal ramp; Cdn$3.0 million for increased surface infrastructure EPCM (Engineering Procurement and Construction Management); and Cdn$10.5 million for additional processing plant equipment, foreign exchange differences and increased structural steel and concrete foundation costs.

The inclusion of the ramp portal, the ITSF and additional processing plant equipment, which will enable the processing plant to process up to 1,500 tonnes of ore per day, were not included in the original scope of the Feasibility Study. The ramp connection to surface will open new production areas sooner in the life-of-mine schedule and will provide operational flexibility. The addition of the ITSF is necessary to begin operations in 2008 due to delays in the federal permitting of Bucko Lake as a tailings storage facility (see Press Release dated March 28, 2008).

Mike Hoffman, Crowflight's President and CEO, said: "One striking advantage of Bucko compared to other mining projects currently being developed throughout the world is that the overall capital costs are moderate in relation to future expected cash flow, especially considering that nickel prices have recently averaged US$12-14 per pound. Many of the cost increases are attributable to scope changes not included in the original Feasibility Study and are designed to add further value to the Bucko Project. These enhancements are necessary to tap into the further potential we believe exists at Bucko. Some of the other cost increases, such as steel and concrete, are consistent with those of other companies currently building mines."

During 2007, Cdn$35.3 million was spent on Bucko construction, which includes the main electrical installation, hoist and headframe installation, processing plant foundations and steel, shaft de-watering and rehabilitation, rehabilitation of the 1000 Level exploration drift, purchasing new and used equipment, refurbishing used equipment and EPCM to date.

Additional information, including Crowflight's Financial Statements and Management Discussion and Analysis, can be found electronically on the System for Electronic Document Analysis and Retrieval ("SEDAR") through Crowflight's profile at www.sedar.com.

The current construction schedule estimates that the commissioning of the processing plant will occur in July and August of 2008, with cash flow from concentrate sales beginning shortly thereafter. Full commercial production is expected in early 2009.

Crowflight Minerals - Canada's Next Nickel Producer

Crowflight Minerals Inc. (TSX VENTURE:CML - News) is a Canadian junior mining exploration and development company focused on nickel, copper and Platinum Group Mineral (PGM) projects in the Thompson Nickel Belt and Sudbury Basin. The Company currently owns and/or has under option approximately 800 square kilometres of exploration and development properties in Manitoba and Ontario.

Crowflight's priority is to bring the fully-funded Bucko Lake Nickel Project located near Wabowden, Manitoba into production by the third quarter of 2008.

Cautionary Note on Forward-Looking Information

Except for statements of historical fact contained herein, the information in this press release constitutes "forward-looking information" within the meaning of Canadian securities law. Such forward-looking information may be identified by words such as "plans", "proposes", "estimates", "intends", "expects", "believes", "may", "will" and include without limitation, statements regarding estimated capital and operating costs, expected production timeline, benefits of updated development plans, foreign exchange assumptions and regulatory approvals. There can be no assurance that such statements will prove to be accurate; actual results and future events could differ materially from such statements. Factors that could cause actual results to differ materially include, among others, metal prices, competition, risks inherent in the mining industry, and regulatory risks. Most of these factors are outside the control of the Company. Investors are cautioned not to put undue reliance on forward-looking information. Except as otherwise required by applicable securities statutes or regulation, the Company expressly disclaims any intent or obligation to update publicly forward-looking information, whether as a result of new information, future events or otherwise.




Total Shares Outstanding:  267.4MM
Fully Diluted:             307.0MM
52-Week Trading Range:     C$0.45 - $1.35


The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this release.



Contact:
Mike Hoffman
Crowflight Minerals Inc.
President and CEO
(416) 861-2964

Heather Colpitts
Crowflight Minerals Inc.
Manager, Investor and Public Relations
(416) 861-5803
Email: info@crowflight.com
Website: www.crowflight.com





Gruß
MadX  

08.05.08 20:34

39 Postings, 6761 Tage steelersanzug

und schon zieht die krähe an und fliegt richtung norden. + 8 % bei tsx. weiter so! ich bin überzeugt, dass das noch lange nicht alles ist. werde morgen nachlegen.  

12.05.08 10:25

270 Postings, 6069 Tage xavierthreegut der Start mit +2,5% ist ganz okay...


kann mir mal jemand von euch einen Link zusenden oder hier reinposten, wo ich erkennen kann wieviele Aktien in CAN gehandelt werden? würde mich mal interessieren.

Hat eigentlich jemand von euch eine bestimmte Seite/Programm wo er Aktienkurse verfolgen kann, welches er mir empfehlen kann?

Please Help Me ;)  

12.05.08 13:15
1

2345 Postings, 6763 Tage reality@xavierthree

Unter diesem Link: http://quickcharts.hmja.de/ wirst Du die Realtimekurse aus Can erhalten und noch viele Informationen mehr wenn Du die Buttons unter der Grafik anklickst.

Gruss  

13.05.08 17:52

247 Postings, 6818 Tage zockerKrähe????????

Kann mir jemand erklären, was hier los ist! Sollte eigentlich im Steilflug gen Himmel sein, aber wo geht sie hin?!


der Zocker  

13.05.08 18:02

9292 Postings, 6851 Tage 2teSpitzeIrgendwie hat die

Krähe Flugangst. Also, Rakete in den A.... und ab in den Himmel. Ist im Moment das Einzige, was hilft.
-----------
*Spitzle2*

13.05.08 19:40

303 Postings, 6565 Tage mr.positivnirgendwo geht sie hin !

sie hält sich wunderbar und nimmt nur anlauf , der erste anstieg war doch nicht schlecht , kurs wird in can gemacht und der steht wenn ich mich nicht irre 0,78 cent ,also locker bleiben, ne kleine konso tut der krähe nur gut .bin guter dinge das wir alle wenn wir gedult haben und dies als langfristiges investment sehen sauuuuuuuu reich werden , wenn bowden mit exploren fertig ist und ne resourcen schätzung vor liegt und wenn man da auch in produktion  geht ,geht es ab hier , meines wissens ist da 10 mal mehr nickel im boden wie jetzt bei buko lake. und jedem sollte klar sein das dann crow wieder anderst bewertet wird .ach ja sollte einer nicht wissen zu wem "bowden" gehört der ziehe sich diese wörter rein -----zu 100 % crowflight minerals -----    

13.05.08 19:45

303 Postings, 6565 Tage mr.positivok hat sich ein fehler

eingeschlichen .... 0,74 cent , die 0,78 war ein olt heut mittag , macht aber auch nichts crow geht seinen weg , außer der dritte weltkrieg bricht aus hi hi  

13.05.08 22:07
3

270 Postings, 6069 Tage xavierthreerichtig mr. positv!

bei Neubewertung wenn Crow erst mal Produzent ist, sind kurse drin um die 2 - 5 Euro drin ;))) und dann will ich in ein paar Jahren kurse um die 10 - 30 Euro sehen ;)  

15.05.08 20:04
4

2345 Postings, 6763 Tage realityRSR-Empfehlung:

Neue Kaufstudie von Versant für Crowflight Minerals
(CAD-Kürzel CML): Die Analysten sehen einen fairen
Wert von 1,10 CAD für den angehenden Nickelproduzenten.
Für 2008 erwartet man bereits einen Nettogewinn von über
36 Mio. CAD, der in 2009 auf 77 Mio. CAD springen soll,
um von 2010 bis 2015 sukzessive von 73 Mio. CAD auf
20,7 Mio. CAD zu sinken. Dies allerdings nur deshalb, weil
man keinerlei Explorationsupgrade auf der Bucko Lake Mine
unterstellt. Crowflight ist auf dem aktuellen Niveau als
Nickelproduzent spottbillig! Dies dürfte nun nicht mehr
lange so bleiben. Denn als größerer Produzent wird man in
naher Zukunft ganz andere Investorenschichten gewinnen
können, die im Explorationsstadium entweder nicht kaufen
dürfen oder wollen.
 

15.05.08 20:12
1

270 Postings, 6069 Tage xavierthreesehr schön... ;)

dann lasst uns mal auf den fairen Wert zusteuern ;)
es wird Zeit dass Crow sich seinem Niveau anpasst.
Es darf losgehen, ich denke da seit ihr alle meiner Meinung ;)

Gruß an jeglichen Investierten, und all diejenigen, die jetzt noch ein-/ zukaufen  

18.05.08 10:57
2

30 Postings, 6118 Tage Saibnun aufwärts !

Man konnte schön sehen wie in canada am freitag der kurs
zum ende schön angestiegen ist mit über 1 Mio. gehandelte Stücke.
Ich denke wir haben nochmals einen kleinen Boden gebildet und
werden nun über die 50cent steigen.
Die Börsen stehen ja nun auf grün und crowflight wird
davon profitieren und bald bei 60 oder 70 cent stehen.
Die Nickelbestände haben auch leicht abgenommen und
ich kann nur sagen kaufen kaufen !
Anhand der Grafik kann man sehen das wir charttechnik
sehr gut da stehen und wir bestenfalls nochmal auf 45 cent fallen
doch dann sollte es bis 55 cent durchgehen.
Wir werden vielleicht schon morgen über 50 cent stehen.  
Angehängte Grafik:
bigchartcazw5elt.png (verkleinert auf 93%) vergrößern
bigchartcazw5elt.png

20.05.08 10:26

722 Postings, 6760 Tage chivalricnur noch eine Frage

der Zeit bis unsere Krähe das Fliegen lernt. Bin aber überzeugt, dass wir den Großteil des Wartens schon hinter uns haben. Dann sollte es aber Schlag auf Schlag gehen.  

20.05.08 14:15

247 Postings, 6818 Tage zockerdie 0,50 wehren sich

aber ordentlich, also Krähe, flieg endlich drüber damit du in weitere
Höhen kommst.:)))

der Zocker  

20.05.08 15:45
1

722 Postings, 6760 Tage chivalricnews - Bohrergebnisse Winterprogramm

Press Release Source: Crowflight Minerals Inc.
Crowflight's Final Results From Winter Exploration Drilling Further Indicate Potential to Expand Bucko Project and Satellite Deposits
Tuesday May 20, 8:48 am ET
TORONTO, ONTARIO--(Marketwire - May 20, 2008) - CROWFLIGHT MINERALS INC. (Crowflight, the Company) (TSX VENTURE:CML - News) today announced final assay results from its 2008 winter exploration drilling program in the Thompson Nickel Belt, Manitoba. Results include hole HW08-11 drilled at Halfway Lake that intersected 15.12 metres (49.6 feet) grading 1.24% nickel, as well as other encouraging assay results from the Halfway Lake and Bucko North target areas.
A key objective of the 2008 winter exploration program was to identify additional sources of potential mill feed proximal to the Company's Bucko Lake Nickel Project (Bucko), located outside Wabowden, Manitoba. The program was successful in identifying new occurrences of mineralization at Halfway Lake, the M11A North Zone and the Bucko North target. These areas are located 20 kilometres, 5 kilometres, and 400 metres respectively from the mill at Bucko, which is scheduled to commence production by the third quarter of 2008.
In summary, 21 holes for a total of 8,200 metres were completed during the winter program. Please refer to Figure 1 for a map depicting the drilling locations and Table 1 for a summary of new and previously-released assays for the 2008 winter program.


Table 1.

Winter 2008 Exploration Program - Summary of Assay Results

--------------------------------------------------
Core Core
Drill Hole From To Length Length Nickel Copper PGEs(1)
---------- ---- -- ------ ------ ------ ------ -------
(metres) (metres) (metres) (feet) (%) (%) (gpt)

Halfway Lake

HW08-01(2) 348.20 351.60 3.40 11.2 0.90 0.08 0.11

and 366.00 370.00 4.00 13.1 0.69 0.05 0.13

HW08-02(2) 334.22 347.25 13.03 42.7 1.58 0.09 0.26

Incl. 334.22 339.45 5.23 17.2 1.76 0.07 0.24

Incl. 338.45 339.45 1.00 3.3 2.44 0.05 0.23

HW08-03(2) No significant assays

HW08-04(2) 183.62 199.23 15.61 50.1 1.03 0.06 0.16

Incl. 198.82 199.23 0.41 1.3 8.35 0.03 2.15

HW08-05(2) 135.66 139.00 3.34 10.7 1.16 0.09 0.16

HW08-06(2) 181.98 182.28 0.30 1.0 5.11 0.27 0.63

HW08-07 No significant assays

HW08-08 No significant assays

HW08-09 No significant assays

HW08-10 186.60 192.69 6.09 20.0 0.97 0.07 0.02

HW08-11 222.95 226.21 3.26 10.7 1.03 0.06 0.02

and 231.79 246.91 15.12 49.6 1.24 0.11 0.03

Incl. 236.69 243.83 7.14 23.4 1.57 0.15 0.04


Bucko North

BX08-01(2) 321.47 330.00 8.53 27.99 0.45 0.02 0.05

BX08-02(2) No significant assays

BX08-03 No significant assays

BX08-04 294.69 295.67 0.98 3.22 1.09 0.05 0.02

and 300.25 300.64 0.39 1.28 2.31 0.05 0.04

and 309.54 309.98 0.44 1.44 1.56 0.21 0.04


M11A Zone

M08-01 403.84 413.84 10.00 32.8 0.59 0.05 0.02

M08-02(2) No significant assays

M08-03(2) 357.05 383.73 26.68 87.5 1.30 0.06 0.41

Incl. 357.05 360.05 3.00 9.8 2.24 0.14 0.75

Incl. 374.54 380.30 5.76 18.9 3.06 0.16 1.02


Apex

Zone

AP08-01(2) No significant assays

AP08-02(2) No significant assays

AP08-03 No significant assays
--------------------------------------------------

(1) Combined platinum and palladium values

(2) Previously reported results - see press releases dated
February 29, 2008 and April 21, 2008


Intersection intervals reported are core lengths; actual true widths are unknown at this time but are generally 70 to 80% of core length. Once known, true widths are calculated for each intersection. These could vary somewhat from time to time as the zones are re-interpreted thereby altering the geometry.
Greg Collins, Vice President of Exploration for Crowflight Minerals, commented on the results of the winter program stating: "The results from the winter exploration program continue to demonstrate the potential of our 700 square kilometre land package in the Thompson Nickel Belt. Drilling at the M11A Zone resulted in the discovery of a new high grade lens, less than 5 kilometres north of milling operations at Bucko. At Halfway Lake, drilling confirmed extensions that we expect to enhance the grade and tonnage of the current resource. Drilling on the Bucko Lake North intrusion has confirmed the presence of higher grade nickel sulphide mineralization at depth less than 400 metres north from the planned underground workings at Bucko. These activities are positive developments for our Company in that they further expand our options for growth at our soon-to-be producing Bucko mine in Wabowden."
Discussion of Results
Halfway Lake
At Halfway Lake, 11 holes totaling 4,529 metres were completed. Highlights include hole HW08-02, intersecting 13.03m grading 1.58% nickel (previously released) and hole HW08-11 which intersected 15.12m grading 1.24% nickel, including 7.14m grading 1.57% nickel. Drilling has confirmed extensions to the previously identified resource that are expected to enhance the grade and tonnage of the known resource.
M11A Zone
Near the M11A target, three holes totaling 1,315 metres were completed. Highlights include hole M08-03, a new high grade lens located beneath the known M11A North resource which intersected 26.7m grading 1.30% nickel including 5.76m grading 3.06% nickel (previously released). Holes M08-01 and M08-02 targeted other portions of the M11A intrusion located more than 500 metres south of the mineralization intersected in M08-03.
Bucko North
Drilling on the Bucko North target included the completion of four holes totaling 1,638 metres. Two holes investigated the near surface potential of the intrusion for condemnation purposes and have confirmed that there is no open pit potential beneath the site of the future tailings storage area. Deeper drilling targeting areas 300 metres below surface confirmed the presence of higher grade nickel sulphide mineralization first identified by drilling in 2007. Hole BX07-01 intersected 7.5 metres grading 0.78% nickel including 1.5m grading 2.19% nickel (previously released). Highlights from hole BX08-04 include narrow intervals of nickel sulphide mineralization containing up to 2.31% nickel. The results of the 2008 program indicate that future work on this target located 400 metres north of planned workings at Bucko may be best achieved once underground access from the Bucko Mine is available.
Apex Zone
Near the Apex target, three holes for 718 metres were completed. The holes were drilled to test exploration targets located more than 500m north and south of the previously defined resource at Apex. One hole (AP08-02) was lost in casing and did not reach its target objective. Holes AP08-01 and AP08-03 intersected magnetic gneiss, explaining the targeted geophysical anomaly. The resource potential at Apex zone remains open for expansion at depth.
Results from this program will be used to generate updated resource calculations at Halfway Lake and M11A North and be used to further refine the focus of resource expansion drilling near Bucko.
2008 Summer Drilling Program at Manibridge
Crowflight and Pure Nickel plan to commence drilling nickel exploration targets identified close to the past-producing Manibridge Mine in early June. Results from this program will be released through the summer and early fall of 2008 as they become available.
Underground Drilling at Bucko
Crowflight continues to conduct underground drilling from the 1,000 foot level of the Bucko Lake Nickel Project, with the intent of obtaining further geotechnical information on the deposit and upgrading the mineral resource and reserve estimates. It is expected that results from this program will be released through the late spring and fall of 2008 as they become available.
Qualified Person/Quality Control Procedures
This press release has been prepared and reviewed by Mr. Greg Collins, P.Geo (APGO/APEGM), who is the Vice President Exploration of the Company and a Qualified Person under the National Instrument 43-101 guidelines. Fire assays were performed at the ALS-Chemex laboratory in Vancouver on all the samples for Gold and PGEs which undergo an ICP-AES finish and Sodium Peroxide Fusion. All other metals undergo an ICP-AES finish at the ALS-Chemex laboratory in Vancouver. Standards and blanks are submitted with each sample batch.
Crowflight Minerals - Canada's Next Nickel Producer
Crowflight Minerals Inc. (TSX VENTURE:CML - News) is a Canadian junior mining exploration and development company focused on nickel, copper and Platinum Group Mineral (PGM) projects in the Thompson Nickel Belt and Sudbury Basin. The Company currently owns and/or has under option approximately 800 square kilometres of exploration and development properties in Manitoba and Ontario.
Crowflight's priority is to bring the fully-funded Bucko Lake Nickel Project located near Wabowden, Manitoba into production by the third quarter of 2008.
Cautionary Note on Forward-Looking Information
Except for statements of historical fact contained herein, the information in this press release constitutes "forward-looking information" within the meaning of Canadian securities law. Such forward-looking information may be identified by words such as "plans", "proposes", "estimates", "intends", "expects", "believes", "may", "will" and include without limitation, statements regarding mineralization projections; mineral reserve and resource estimates; scheduled exploration programs and costs thereof; estimated capital and operating costs; expected production timeline; requirements for additional financing. There can be no assurance that such statements will prove to be accurate; actual results and future events could differ materially from such statements. Factors that could cause actual results to differ materially include, among others, ability to realize mineral reserve and resource estimates; ability to obtain financing; metal prices, competition, risks inherent in the mining industry, including risks relating to mine development, and regulatory risks. Most of these factors are outside the control of the Company. Investors are cautioned not to put undue reliance on forward-looking information. Except as otherwise required by applicable securities statutes or regulation, the Company expressly disclaims any intent or obligation to update publicly forward-looking information, whether as a result of new information, future events or otherwise.
To view Figure 1. 2008 Winter Exploration Program Location Map, please visit the following link: http://media3.marketwire.com/docs/CROW0520b.pdf.
Total Shares Outstanding: 267.4MM
Fully Diluted: 307.0MM
52-Week Trading Range: C$0.45 - $1.29
The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this release.
 

20.05.08 16:11

303 Postings, 6565 Tage mr.positivhier in deutsch

Pressemitteilung Quelle: Crowflight Minerals Inc.
Crowflight die endgültigen Ergebnisse aus Winter Exploration Drilling weiter angeben, das Potenzial zur Steigerung Bučko Projekt-und Satelliten-Einlagen
Dienstag 20. Mai, 8.48 Uhr ET
TORONTO, ONTARIO - (Marketwire - 20. Mai 2008) - CROWFLIGHT MINERALS INC (Crowflight, die Firma) (TSX Venture: CML - News) gab heute bekannt, endgültig Assay Ergebnisse aus seinem 2008 Winter Exploration Bohren Programm in der Thompson Nickel Belt, Manitoba. Die Ergebnisse beinhalten Loch HW08-11 gebohrt auf halbem See, zusammentrafen 15,12 Meter (49,6 Fuß) Einstufung von 1,24% Nickel, sowie andere ermutigend Test ergibt sich aus der Halfway Lake Bučko Nord-und Zielbereiche.
Ein wesentliches Ziel der 2008 Winter Exploration-Programm wurde zur Ermittlung zusätzlicher Quellen potenzieller Mühle-Feed von proximalen Gelenken des Unternehmens Bučko Lake Nickel Project (Bučko), die außerhalb Wabowden, Manitoba. Das Programm wurde erfolgreich bei der Ermittlung neuer Vorkommen von Mineralen auf halbem See, der M11A Nord-Zone und der Norden Bučko Ziel. Diese Gebiete liegen 20 Kilometer, 5 Kilometer und 400 Meter jeweils aus der Mühle in Bucko, das ist für die Produktion im dritten Quartal 2008.
Zusammenfassend lässt sich sagen, 21 Löcher mit einem Gesamtvolumen von 8200 Metern wurden während der Winter-Programm. Bitte beziehen Sie sich auf Abbildung 1 für eine Karte der Darstellung der Bohr-Standorten und Tabelle 1 für eine Zusammenfassung der neuen und zuvor freigegeben Assays für die Winter-Programm 2008.


Tabelle 1.

Winter 2008 Exploration Program - Zusammenfassung der Assay-Ergebnisse

-------------------------------------------------- -----------------------
Core Core
Bohrung von bis Länge PGEs Nickel-Kupfer (1)
---------- ---- - ------ ------ ------ ------ -------
(m) (m) (m) (m) (%) (%) (GPT)

Halfway Lake

HW08-01 (2) 348,20 351,60 3,40 11,2 0,90 0,08 0,11

und 366,00 370,00 4,00 13,1 0,69 0,05 0,13

HW08-02 (2) 334,22 347,25 13,03 42,7 1,58 0,09 0,26

Inkl. 334,22 339,45 5,23 17,2 1,76 0,07 0,24

Inkl. 338,45 339,45 1,00 3,3 2,44 0,05 0,23

HW08-03 (2) keine nennenswerten Assays

HW08-04 (2) 183,62 199,23 15,61 50,1 1,03 0,06 0,16

Inkl. 198,82 199,23 0,41 1,3 8,35 0,03 2,15

HW08-05 (2) 135,66 139,00 3,34 10,7 1,16 0,09 0,16

HW08-06 (2) 181,98 182,28 0,30 1,0 5,11 0,27 0,63

HW08-07 keine nennenswerten Assays

HW08-08 keine nennenswerten Assays

HW08-09 keine nennenswerten Assays

HW08-10 186,60 192,69 6,09 20,0 0,97 0,07 0,02

HW08-11 222,95 226,21 3,26 10,7 1,03 0,06 0,02

und 231,79 246,91 15,12 49,6 1,24 0,11 0,03

Inkl. 236,69 243,83 7,14 23,4 1,57 0,15 0,04


Bučko Nord

BX08-01 (2) 321,47 330,00 8,53 27,99 0,45 0,02 0,05

BX08-02 (2) keine nennenswerten Assays

BX08-03-Assays keine signifikanten

BX08-04 294,69 295,67 0,98 3,22 1,09 0,05 0,02

und 300,25 300,64 0,39 1,28 2,31 0,05 0,04

und 309,54 309,98 0,44 1,44 1,56 0,21 0,04


M11A-Zone

M08-01 403,84 413,84 10,00 32,8 0,59 0,05 0,02

M08-02 (2) keine nennenswerten Assays

M08-03 (2) 357,05 383,73 26,68 87,5 1,30 0,06 0,41

Inkl. 357,05 360,05 3,00 9,8 2,24 0,14 0,75

Inkl. 374,54 380,30 5,76 18,9 3,06 0,16 1,02


Apex

Zone

AP08-01 (2) keine nennenswerten Assays

AP08-02 (2) keine nennenswerten Assays

AP08-03 keine nennenswerten Assays
-------------------------------------------------- -----------------------

(1) Kombinierte Platin und Palladium-Werte

(2) Publiziert Ergebnisse - siehe Pressemitteilungen vom
29. Februar 2008 und 21. April 2008


Intersection Abständen gemeldet sind zentrale Längen, die tatsächlich wahr Breiten unbekannt sind in dieser Zeit aber sind in der Regel 70 bis 80% der Kern-Länge. Sobald bekannt ist, wahre Breite werden berechnet für jeden Schnittpunkt. Diese könnten ein wenig variieren von Zeit zu Zeit wie die Zonen sind neu interpretiert und damit eine Änderung der Geometrie.
Greg Collins, Vice President of Exploration Crowflight Minerals, kommentierte die Ergebnisse des Winter-Programms lautet: "Die Ergebnisse aus dem Winter Exploration Programm auch weiterhin unter Beweis stellen das Potenzial unserer 700 Quadratkilometer Land Paket in der Thompson Nickel Belt. Bohren in der M11A Zone führte zur Entdeckung einer neuen High-Grade-Objektiv, weniger als 5 Kilometer nördlich von Fräs-Operationen in Bučko. Auf halbem See, Bohren bestätigt, Erweiterungen, die wir erwarten, zur Verbesserung der Qualität und Menge der aktuellen Ressource. Bohren in der Bučko See Nord-Intrusion hat bestätigt, die Präsenz der höheren Besoldungsgruppe Nickel-Sulfid-Mineralisierung in der Tiefe von weniger als 400 Meter nördlich von der geplanten unterirdischen Arbeiten in Bučko. Diese Aktivitäten sind positive Entwicklungen für unser Unternehmen, dass sie im weiteren Ausbau unserer Optionen für Wachstum in unserer bald-zu - produziert Bučko Mine in Wabowden. "
Diskussion der Ergebnisse
Halfway Lake
Auf halbem See, 11 Löcher in Höhe von insgesamt 4529 Metern wurden fertig gestellt. Highlights zählen Loch HW08-02, kreuzende 13.03m Einstufung von 1,58% Nickel (vorher freigegeben) und Loch HW08-11 die sich 15.12m Einstufung von 1,24% Nickel, einschließlich 7.14m Einstufung von 1,57% Nickel. Bohren Erweiterungen hat bestätigt, dass die zuvor identifizierten Ressource, die voraussichtlich zur Verbesserung der Qualität und Menge der bekannten Ressource.
M11A-Zone
In der Nähe des M11A Ziel, drei Löcher in Höhe von 1315 Metern wurden fertig gestellt. Highlights zählen Loch M08-03, eine neue hochwertige Objektiv befindet sich unter der bekannten M11A Nord-Ressource, die zusammentrafen 26.7m Einstufung von 1,30% Nickel einschließlich 5.76m Einstufung von 3,06% Nickel (vorher freigegeben). Löcher M08-01 und M08-02 gezielte andere Teile der M11A Intrusion befindet sich mehr als 500 Meter südlich der Mineralisierung intersected in M08-03.
Bučko Nord
Bohren in der Nord-Bučko Ziel gehörten die Fertigstellung der vier Löcher in Höhe von 1638 Metern. Zwei Löcher untersucht die oberflächennahen Potenzials der Eingriff für Zwecke Verurteilung und haben bestätigt, dass es keine offene Grube Potenzial unter dem Gelände des künftigen Bergematerial Lagerraum. Tiefere Bohrungen gezielt Bereiche 300 Meter unter der Oberfläche bestätigt Anwesenheit von höheren Besoldungsgruppe Nickel-Sulfid-Mineralisierung zum ersten Mal durch Bohrungen in 2007. Hole BX07-01 durchschnitt 7,5 Meter Einstufung von 0,78% Nickel, einschließlich 1,5 m Einstufung von 2,19% Nickel (vorher freigegeben). Highlights von Loch BX08-04 gehören engen Abständen von Nickel-Sulfid-Mineralisierung mit bis zu 2,31% Nickel. Die Ergebnisse der 2008-Programm deuten darauf hin, dass die künftige Arbeit auf dieses Ziel befindet sich 400 Meter nördlich der geplanten Arbeiten im Mai Bučko am besten erreicht werden, sobald unterirdischen Zugang vom Bučko Mine zur Verfügung steht.
Apex-Zone
In der Nähe des Apex Ziel, drei Löcher für 718 Meter wurden fertig gestellt. Die Löcher wurden gebohrt, um Explorations-Ziele befindet sich mehr als 500 m nördlich und südlich der zuvor definierte Ressource an der Spitze. Ein Loch (AP08-02) wurde verloren im Gehäuse und nicht ihr Ziel erreichen Ziel. Löcher AP08-01 und AP08-03 intersected magnetischen Gneis, erläutert die gezielte geophysikalischen Anomalie. Die potenzielle Ressource im Apex-Zone bleibt offen für eine Expansion in der Tiefe.
Ergebnisse aus diesem Programm wird benutzt, um aktualisierte Ressource-Berechnungen auf halbem See und M11A Nord-und verwendet werden, um weitere Verfeinerung der Schwerpunkt der Expansion Bohr-Ressource in der Nähe von Bučko.
Sommer 2008 Drilling Program Manibridge
Crowflight und Reinnickel Plan zur Aufnahme der Bohr-Nickel Exploration Ziele identifiziert nahe der Vergangenheit produzierenden Manibridge Mine Anfang Juni. Ergebnisse aus diesem Programm wird durch die im Sommer und frühen Herbst 2008, sobald sie verfügbar sind.
U-Bohren in Bučko
Crowflight weiter zu führen unterirdische Bohrungen aus dem 1000 Fuß Höhe der Bučko Lake Nickel Project, mit der Absicht der Erlangung von geotechnischen weitere Informationen über die Hinterlegung und den Ausbau der mineralischen Ressourcen-und Reserve-Schätzungen. Es wird erwartet, dass die Ergebnisse aus diesem Programm wird durch den späten Frühling und im Herbst 2008, sobald sie verfügbar sind.
Qualifizierte Person / Quality Control Verfahren
Diese Pressemitteilung wurde bearbeitet und überprüft von Herrn Greg Collins, P. Geo (APGO / APEGM), ist der Vice President Exploration des Unternehmens und eine qualifizierte Person gemäß dem National Instrument 43-101 Leitlinien. Fire-Assays wurden in der ALS Chemex-Labor in Vancouver in allen Proben für Gold-und PGEs die sich einer ICP-AES Finish und Natrium Peroxidzahl Fusion. Alle anderen Metallen unterziehen ein ICP-AES Finish in der ALS Chemex-Labor in Vancouver. Standards und Blanks sind, die mit jeder Probe Partie.
Crowflight Minerals - Canada's Next Nickel-Produzent
Crowflight Minerals Inc. (TSX Venture: CML - News) ist ein kanadisches Junior-Explorations-und Bergbau-Entwicklung Unternehmen, das sich auf Nickel, Kupfer und Platin-Gruppe Mineral (PGM) Projekten in der Thompson Nickel Belt und die Sudbury-Becken. Das Unternehmen derzeit besitzt und / oder hat unter Option rund 800 Quadratkilometern der Erforschung und Entwicklung Eigenschaften in Manitoba und Ontario.
Crowflight Es ist ein vorrangiges Anliegen, um die voll-finanzierten Bučko Lake Nickel-Projekt befindet sich in der Nähe von Wabowden, Manitoba in die Produktion im dritten Quartal 2008.
Cautionary Hinweis auf zukunftsorientierte Informationen
Mit Ausnahme von Aussagen zu historischen Tatsache hierin enthaltenen, die Informationen in dieser Pressemitteilung stellen "zukunftsgerichtete Informationen" im Sinne des kanadischen Wertpapierrechts. Solche zukunftsgerichteten Angaben können erkennbar durch Formulierungen wie "plant", "schlägt", "schätzt", "beabsichtigt", "erwartet", "glauben", "Mai", "werden" und umfassen ohne Einschränkung Aussagen in Bezug auf Mineralisierung Projektionen; mineralischen Reserven und Ressourcen-Schätzungen; geplanten Exploration Programme und Kosten; geschätzten Kapital-und Betriebskosten; erwarteten Produktion Timeline; Anforderungen an zusätzlicher Finanzierung. Es kann keine Garantie dafür, dass solche Aussagen wird sich als zutreffend; tatsächlichen Ergebnisse und zukünftige Ereignisse können sich wesentlich von diesen Aussagen. Faktoren, die dazu führen, dass tatsächliche Ergebnisse erheblich abweichen, zählen unter anderem, die Fähigkeit zu erkennen, mineralischen Reserven und Ressourcen-Schätzungen; Fähigkeit zu erlangen Finanzierung; Metall-Preise, Wettbewerb, Risiken in der Bergbauindustrie, einschließlich der Risiken im Zusammenhang mit Mine Entwicklung und regulatorische Risiken . Die meisten dieser Faktoren liegen außerhalb der Kontrolle des Unternehmens. Die Anleger sind daher nicht zu Unrecht zu setzen Vertrauen in die Zukunft gerichtete Aussagen. Soweit nicht anders beschrieben von Wertpapieren anwendbaren Gesetze oder Regelungen, die Gesellschaft lehnt ausdrücklich jede Absicht oder Verpflichtung zur Aktualisierung öffentlich die Zukunft gerichtete Aussagen, Informationen, unabhängig davon, ob infolge neuer Informationen, zukünftiger Ereignisse oder aus sonstigen Gründen.
So zeigen Abbildung 1. Winter 2008 Exploration Program Anfahrtsskizze finden Sie unter dem folgenden Link: http://media3.marketwire.com/docs/CROW0520b.pdf.
Insgesamt ausstehenden Aktien: 267.4MM
Fully diluted: 307.0MM
52-Week Trading-Range: C $ 0,45 - $ 1,29
Die TSX Venture Exchange übernimmt keine Verantwortung für die Angemessenheit oder Genauigkeit dieser Freigabe.
 

21.05.08 09:16

30 Postings, 6118 Tage Saiblet´s go !

könnte ein schöner tag heute werden
die sonne scheint ja schon non stop.  

21.05.08 10:32

30 Postings, 6118 Tage Saibwenn die 0.50 durch sind dann gehts aufwärts !

21.05.08 15:29
1

303 Postings, 6565 Tage mr.positivhier was interessantes zum lesen

München (aktiencheck.de AG) - Der Nickelpreis ist in der letzten Woche auf den niedrigsten Stand seit Februar dieses Jahres gefallen, ging dann aber unverändert aus der Woche, so die Experten von "BörseGo" in ihrem "Rohstoff-Report". Stützend habe sich ein Rückgang der LME-Lagerbestände auf den Nickelpreis ausgewirkt. Das erste Mal seit Anfang März seien die Nickelvorräte in London unter die 50.000-Tonnen-Grenze gefallen. Auf Seiten der Nachrichten habe in der letzten Woche ThyssenKrupp AG auf sich aufmerksam gemacht. Der größte Stahlhersteller Deutschlands habe einen Anstieg des Auftragseingangs um 40% im vierten Quartal 2007 und im ersten Quartal 2008 gemeldet. Viele Stahlhändler hätten in den vergangenen Monaten ihre Lagerbestände geleert und würden nun beginnen, diese durch neue Einkäufe wieder aufzufüllen. Das dürfte zu einer steigenden Nickelnachfrage führen und den Preis auf dem aktuellen Niveau stützen. (Ausgabe 10 vom 13. bis 20. Mai 2008) (21.05.2008/ac/a/m)
 

22.05.08 11:00
1

960 Postings, 6393 Tage ZwenerArtikel über das Bohprogramm

23.05.08 14:22

247 Postings, 6818 Tage zocker????

was ist denn jetzt los??  

23.05.08 15:34
2

960 Postings, 6393 Tage Zwenerliegt am Nickelpreis

jetzt werden wieder einige "zittrige" zurückgelassen :)

Ich hab mit meinen crows schon die 0,28 Kursregion angetestet! So was bringt mich nicht aus der Ruhe!  

Seite: Zurück 1 | ... | 36 | 37 | 38 |
| 40 | 41 | 42 | ... | 76  Weiter  
   Antwort einfügen - nach oben